At FMG, a bathroom remodel typically involves about two to three weeks of main construction work. Planning, material deliveries, permits and custom shower glass can extend the overall schedule. Before agreeing on a start date, confirm what must be ready, when your bathroom will be unavailable and whether any final installation will happen after the main work.
A bathroom remodel changes your daily routine before it changes the room. Knowing when you will lose access to the shower, which materials need to be ready and what happens next makes that temporary disruption easier to plan around.
The schedule for your bathroom remodel depends on the scope, the condition of the existing space, material availability and any required inspections. Planning, ordering and permit processing happen before or around the construction period and need their own place in the schedule.
When we remodel two or three bathrooms together, the duration does not simply multiply by the number of rooms. Some work can be coordinated across them. The sequence also needs to take account of which bathroom your household can continue using.
Once the contract is signed, materials should be on site, or we should have an agreed plan to collect them. You can buy from the suppliers you prefer; the important part is knowing exactly what has been ordered and when it will be available.
One of the most common causes of delay in our bathroom projects is a missing tub or rough-in plumbing component. These items can be needed as early as the second or third day, even though the finished bathroom is still some way off.
The rough-in valve is the part of a shower faucet installed inside the wall. The visible handle and trim may be sold separately. Before ordering, check that the selected parts are compatible and that your order includes everything needed for installation. A box containing the shower trim is not always the complete faucet package. Delta’s guide explains the distinction.
Keep model numbers and installation instructions together, and check deliveries for missing pieces or damage. It is much easier to resolve an ordering problem while the existing bathroom is still usable.
The following ranges describe typical working time for individual stages in an FMG bathroom remodel:
Where electrical work is included, rough and finish electrical work typically accounts for another 1–2 working days across the relevant stages.
For a vanity countertop, the 3–5-day planning range starts when the template is taken from the installed vanity. That work is normally coordinated alongside other activities rather than automatically added at the end.
When permits are required, allow approximately 3–5 additional days in the project schedule, separate from the time needed to obtain the permits themselves. FMG uses roughly a week for that permit-processing allowance when planning, but the actual timing depends on the project and the permitting authority.
Standard shower glass can be installed as soon as the shower is ready and the glass is available. Custom glass is measured after the tile is installed. Fabrication typically takes about a week after measurement; in FMG’s usual sequence, installation often happens two or three days after the main remodeling work is finished. Confirm that final glass-installation date as part of your project schedule.
These ranges are a guide to the work involved, not a day-by-day promise. Some activities overlap; others must wait for the preceding work to be ready. Custom glass, countertop arrangements, inspections and material requirements all need to be reflected in the project-specific schedule.
Mortar, waterproofing products, grout and other materials have installation and curing requirements. The next stage cannot always begin as soon as the previous task looks finished.
For example, Schluter recommends waiting at least 24 hours after installing KERDI before beginning a water test under normal curing conditions. The test itself also takes time. That is why the working time for installing waterproofing should not be confused with the full elapsed time before the shower is ready for tile.
At FMG, we do not start a project and then leave it for several days to work on another job. When the sequence requires a pause for curing, an inspection or a separately scheduled installation, we explain what is happening and what comes next.
Our La Jolla two-bathroom renovation is a useful example. The published project description includes replacement of deteriorated subflooring, upgrades to aging underground plumbing, oversized slab tile, a curbless shower and a freestanding bathtub.
Those are different tasks from replacing finishes in their existing locations. They show why two bathrooms with similar floor areas can need different construction plans. The schedule should reflect those individual tasks rather than the floor area alone.
If demolition reveals a condition that was not part of the original scope, we discuss the options and cost before proceeding with additional work. Any effect on the schedule needs to be considered at the same time.
Before work begins, clear the bathroom and set aside the toiletries, medicines and other items you will need each day. Decide which bathroom will serve the household during construction. If it is your only bathroom, discuss that practical limitation before agreeing on the start date.
Agree on access to the house, a place for delivered materials and a clear route to the work area. Let us know about pets, children, work-from-home needs or building restrictions that affect how the day should be organized.
A bathroom is a confined workspace, so a typical FMG crew is one or two people, with the appropriate trades involved at different stages. More people in the room would not necessarily make the work move faster. Debris is generally hauled away about once a week; the temporary collection area should be agreed in advance.
The most useful schedule is one built around your actual bathroom: the agreed work, the materials, the household's needs and the steps that have to happen in order.